Quantcast
Channel: SCN: Message List
Viewing all articles
Browse latest Browse all 8545

Re: Budget Release Error

$
0
0

Hi, Mazal,

 

It looks you have assigned some commitments under project before creating & releasing budget & now you are going to create and release budget.

 

The Error comes because, commitment values are greater than budget release.

 

Go in CJ32 by entering project def. share the screen shot. Don't share error screen over.

 

 

With regards,

Dnyanesh


Viewing all articles
Browse latest Browse all 8545

Trending Articles